Name | Category | Final Depth (m) | RL Top (m) | Latitude | Longitude | Location Method▲ | Date Completed | Project | ||
---|---|---|---|---|---|---|---|---|---|---|
BH19 | borehole | 12.00 | 4.500 | -27.46711718 | 153.0091337 | estimated-rough | 2000-11-02 | Lang Park Redevel... | file | |
BH20 | borehole | 10.30 | 26.200 | -27.46595593 | 153.0131576 | estimated-rough | 2000-11-14 | Lang Park Redevel... | file | |
BH21 | borehole | 10.10 | 26.000 | -27.46580063 | 153.0135626 | estimated-rough | 2000-11-14 | Lang Park Redevel... | file | |
BH22 | borehole | 10.35 | 25.800 | -27.46567519 | 153.0138839 | estimated-rough | 2000-11-14 | Lang Park Redevel... | file | |
BH23 | borehole | 8.00 | 19.300 | -27.46576263 | 153.0148836 | estimated-rough | 2000-11-16 | Lang Park Redevel... | file | |
BH24 | borehole | 6.90 | 19.800 | -27.4656594 | 153.0152314 | estimated-rough | 2000-11-16 | Lang Park Redevel... | file | |
BH25 | borehole | 15.10 | 19.000 | -27.46599717 | 153.0144078 | estimated-rough | 2000-11-16 | Lang Park Redevel... | file | |
BH26 | borehole | 19.50 | 19.000 | -27.46546561 | 153.0162076 | estimated-rough | 2000-11-17 | Lang Park Redevel... | file | |
BH27 | borehole | 11.80 | 19.000 | -27.46595358 | 153.0143672 | estimated-rough | 2000-11-20 | Lang Park Redevel... | file | |
BH28 | borehole | 11.70 | 15.200 | -27.46558797 | 153.0157032 | estimated-rough | 2000-11-18 | Lang Park Redevel... | file | |
BH29 | borehole | 8.00 | 5.000 | -27.46780925 | 153.0078702 | estimated-rough | 2000-11-21 | Lang Park Redevel... | file | |
BH30 | borehole | 14.00 | 4.800 | -27.46767164 | 153.0082671 | estimated-rough | 2000-11-21 | Lang Park Redevel... | file | |
BH31 | borehole | 13.50 | 4.900 | -27.46750536 | 153.0087496 | estimated-rough | 2000-11-22 | Lang Park Redevel... | file | |
BH32 | borehole | 6.70 | 7.700 | -27.46717865 | 153.0096702 | estimated-rough | 2000-11-22 | Lang Park Redevel... | file | |
BH33 | borehole | 8.35 | 15.000 | -27.46847841 | 153.005886 | estimated-rough | 2000-11-23 | Lang Park Redevel... | file | |
BH34 | borehole | 7.45 | 15.300 | -27.46865367 | 153.005353 | estimated-rough | 2000-11-23 | Lang Park Redevel... | file | |
BH35 | borehole | 10.35 | 10.000 | -27.46813473 | 153.0071485 | estimated-rough | 2000-11-29 | Lang Park Redevel... | file | |
TP1 | test pit | 1.60 | 3.800 | -27.46595636 | 153.0087871 | estimated-rough | 2000-10-25 | Lang Park Redevel... | file | |
TP2 | test pit | 2.70 | 8.500 | -27.46585601 | 153.0091492 | estimated-rough | 2000-10-25 | Lang Park Redevel... | file | |
TP3 | test pit | 3.80 | 7.500 | -27.46531068 | 153.0102761 | estimated-rough | 2000-10-25 | Lang Park Redevel... | file |